tool name

close
tool goes here

Bridge update: March 4, 2007

Published: March 4, 2007 at 7:34 a.m. PST
0 comments

Construction this week on the new Tacoma Narrows bridge:

Crews pasting and wrapping the main cables have refined their techniques to deal with wet weather and are beginning to make good progress.

As of Friday, 12 of 270 “bays” had been wrapped. (A bay is the approximately 40-foot space between suspender hangers. Each takes 3.3 miles of wrapping wire.)

This week all four wrapping machines will operate – two near the top of the Tacoma tower, working their way down toward the anchorage, and two at the Gig Harbor anchorage, working their way up.

Most of the bolting needed to permanently join the 46 deck sections will be finished this week. That will leave only the bolts on some diagonals and those on the U-ribs that support the top deck plates. The U-rib bolts can’t be permanently tightened until the top plates are welded together.

The welding crews are forging ahead. At the end of last week they had finished 15 of 45 joints.

Crews installed gantries over the 24th Street on-ramp to the bridge in Gig Harbor last week to accommodate transponder-reading devices for the “Good to Go” automatic toll-collection system.

This week, they’ll install electrical conduit lines and electronic hardware at the gantries.

Why is the deck of the new bridge higher in the middle than the old one? – Karen P., Gig Harbor

The two decks weren’t designed to match precisely. They’ll be closer to the same level when the new one is paved. Paving material will constitute 15 percent of the total weight of the deck.

Rob Carson, The News Tribune

JOIN THE DISCUSSION | Register here

We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.

CONTESTS

Similar stories

  • Crews will renovate Weiser bridge in May

    The concrete deck of the new bridge built several years ago over the Snake River connecting Annex, Oregon to Weiser, Idaho on the U.S. 95 Spur will be sealed starting May 6 with an epoxy overlay to extend its life.

    The work is a short-duration project, spanning two weeks. The epoxy helps to seal and protect the deck of the new bridge, keep the salts out, stop corrosion, and extend the life of the new structure. The $10 million bridge project was completed in 2010.

    Crews are expected to work a 7 a.m. to 7 p.m. if weather allows. Drivers will be limited to one lane across the bridge, with traffic controlled by a temporary signal at the end of the bridge. The other half of the bridge will be shut down for work.

  • Evening lane closures this week on Narrows Bridge

    Lane closures on the westbound Tacoma Narrows Bridge could cause evening backups this week, according to the state Department of Transportation.

  • Narrows Bridge to close two nights this week

    Crews working for the state Department of Transportation will close two westbound state Route 16 lanes across the 1950 Tacoma Narrows Bridge on two nights this week.

  • Donkey Creek project snarls traffic, cuts into business in Gig Harbor

    Businesses and residents are feeling the pinch from a major construction project in downtown Gig Harbor that will cause traffic delays through the summer tourism season.

  • Owners say boats damaged during Murray Morgan Bridge restoration

    Contractors pressure washing, welding and working on the Murray Morgan Bridge over the Thea Foss Waterway have apparently rained a cloud of metal filings, paint, rivets, bolts and other debris on the boats below. Although no one has been injured, boat owners point to holes in the metal roofs of the sheds that shelter some of the boats.