Question: Is the cross-base highway ever going to be finished? Claude Whitley, Puyallup
Answer: That remains to be seen.
The first phase of the project has been completed at a cost of $9.5 million, and another $31.5 million has been spent on studies and buying rights of way.
But theres no money for the rest of the job, and work has been suspended.
Were waiting for the funding, said Washington State Transportation Department spokeswoman Claudia Bingham Baker. Well build as much as the Legislature will fund.
The estimated cost of completing the project was $419.6 million in 2008, when it was last calculated. That estimate doesnt include redoing the interchange at Interstate 5 and Thorne Lane. The controversial project would construct a new state Route 704 across Joint Base Lewis-McChord, linking state Route 7 (Pacific Avenue) to Interstate 5.
Have a question about traffic congestion, construction, spending or other transportation issues? Send it to traffic@thenews tribune.com. Include your name, hometown and daytime telephone number. Well answer as many as we can.


JOIN THE DISCUSSION | Register here
We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.