Sea-Tac Airports 40-year-old North Satellite Terminal will undergo an estimated $230 million remodeling and expansion to bring the terminal up to 21st century standards, the airports owner announced this week.
The Port of Seattle Commission this week gave final approval to begin designs for the terminal renovation. Actual construction is expected to start in 2014 with completion two years later. The terminal will remain open during the overhaul.


JOIN THE DISCUSSION | Register here
We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.