I-5 gets facelift in Federal Way area; $6.7 million project to replace concrete panels

Construction crews who spent much of the summer repairing portions of road surface on Interstate 5 in Tacoma have moved to South King County, where they’re working on a notoriously bumpy section of freeway north of Federal Way.

Published: Nov. 5, 2012 at 10:44 a.m. PSTUpdated: Nov. 5, 2012 at 10:06 a.m. PST
0 comments

Construction crews who spent much of the summer repairing portions of road surface on Interstate 5 in Tacoma have moved to South King County, where they’re working on a notoriously bumpy section of freeway north of Federal Way.

With a budget of $6.7 million, workers are cutting out and replacing 64 deteriorated concrete panels and smoothing three miles of northbound I-5 between Military Road South and South 260th Street.

The work is taking place between 9 p.m. and 5 a.m. to minimize delays, said Broch Bender, a state Department of Transportation spokeswoman.

Nighttime lane closures began Oct. 22 and will continue through spring, when the project is scheduled to be completed, Bender said.

Crews are using the closures to replace cracked or broken 12-by-15-foot sections of concrete that form the driving surface. They’ll also use diamond-tipped blades to grind down the worn surface and remove ruts worn by tires, a process intended to extend the life of the concrete and provide a smoother ride.

The panel work is expected to be completed by December, the Transportation Department said. The grinding work will begin in mid-winter and continue through spring.

The project is financed by the state gas tax.

The project is in keeping with a policy of triage on I-5 in which repairs are undertaken on “the worst of the worst” sections, Transportation Department officials said.

The triage approach is not new to I-5. Two years ago, crews replaced 295 concrete panels on 25.5 miles of I-5 between Martin Way in Lacey and 48th Street in Tacoma.

This summer, crews replaced 75 damaged concrete panels on I-5 between 48th and M streets in Tacoma. In addition to replacing the concrete panels, crews ground more than five miles of freeway surface.

The interstate is made up of thousands of concrete panels joined by steel dowel bars. It takes 350 panels to make up one lane on a mile of freeway. A four-lane, mile-long section of I-5 contains 1,400 panels.

The steel bars linking the panels are flexible enough to bend slightly with the weight of traffic.

The pavement on I-5 through Pierce, King and Thurston counties is more than 50 years old, which Bender notes is more than twice its expected 20-year design life.

“The freeway in this area predates the Space Needle,” Bender said. “The whole thing really needs to be replaced, but that’s a $2 billion fix and there’s no money for that now.”

Between now and 2019, the Transportation Department has identified – and the Legislature has funded – nearly $130 million worth of concrete rehabilitation projects on state highways.

Rob Carson 253-597-8693

rob.carson@thenewstribune.com

JOIN THE DISCUSSION | Register here

We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.

Fifty years of wear are visible in the surface of Interstate 5 between Tacoma and Seattle. In the background, contractors cut out a section of concrete in a northbound lane of Interstate 5 at South 272nd street in Federal Way. (PETER HALEY/Staff photographer)
MORE PHOTOS
CONTESTS

Similar stories

  • Major road projects to expect this spring, summer in Whatcom County

    The rainy season is giving way to construction season, and drivers in every corner of Whatcom County are bound to encounter closed lanes and detours in the months ahead.

    The state Department of Transportation doesn't have a lot of big-ticket projects in Whatcom County this year. The state's most significant work will take place on Meridian Street, between Interstate 5 and Horton Road. The agency and the contractor plan to close lanes only at night.

    Another big Bellingham project, this one being handled by the city, is a roundabout at the intersection of Boulevard, State Street, North Forest Street and Wharf Street. This will meet immediate safety needs and serve future development of the waterfront at the bottom of Wharf Street.

  • 38th Street exit closure will create I-5 backups

    It could be a long summer for Tacoma commuters. Traffic engineers at the state Department of Transportation say a three-month closure of one of the city’s busiest freeway off-ramps will cause daily backups that could stretch for miles in both directions of Interstate 5.

  • Part of old Nalley Valley viaduct falls onto road

    A large section of the old Nalley Valley viaduct unexpectedly toppled onto South Tacoma Way on Friday afternoon as demolition crews chipped away at it from below.

  • Parts of I-5, Route 16 to close for work

    Drivers in Tacoma will have to contend with two freeway closures tonight.

  • Seattle tunnel creates jobs in Pierce County

    A sign prominently posted on Canyon Road East, near the entrance to FPS-Encon Precast’s expanded Frederickson plant, explains in short measure why dignitaries are gathering at the plant Wednesday to celebrate. “Now hiring,” the sign declares