Port of Bellingham, city have new strategy for building up waterfront

Published: Dec. 28, 2012 at 6:00 p.m. PSTUpdated: April 19, 2013 at 11:30 a.m. PDT
0 comments
The Granary Building on Bellingham's waterfront was built in 1928 as the focal point of a once-booming egg and poultry business in Whatcom County. It has been vacant for decades, and was the property of Georgia-Pacific Corp. before that company shut down its waterfront pulp and paper operations and handed over its 137 acres of industrial land to the port in 2005. (PHILIP A. DWYER/THE BELLINGHAM HERALD)

BELLINGHAM - When the Port of Bellingham acquired the Georgia-Pacific Corp. pulp and paper mill site, the potential cost of environmental cleanup was a big, worrisome unknown.

The port's preliminary estimate of that cost was $40.3 million, but nobody knew for sure the extent of contamination from decades of pulp and chemical operations that involved mercury, among other things, or what it would cost to deal with that contamination in a way the Washington Department of Ecology would accept.

So in late 2004, before closing the deal with G-P, port officials arranged the purchase of a complex insurance policy to cover potential overruns.

Eight years later, that looks like a pretty good investment. Port Environmental Director Mike Stoner said cleanup costs will likely total about $102 million, but the insurance policy should enable the port to cover the added cost, partly because payments from the policy can be used as matching money for state cleanup funds.

While the full cleanup of the waterfront and adjoining waters is still years away, there is some good news: Contamination at the northern end of the site around the Granary Building is comparatively minor. Stoner said cleanup of that area could be complete by the end of 2013.

If the city and port can complete master planning and land-use regulations to lay the legal groundwork, the job of recruiting private investment in the waterfront could begin in earnest. Then, actual buildings could go up, but probably not before 2015 or 2016, said Tara Sundin, one of the city's lead planners on waterfront issues.

IMPROVEMENTS PLANNED

The city also faces millions in expenses before that day comes. The city must build the streets, sidewalks and parks that will make the industrial ghost town an attractive opportunity for private developers. The city then recoups its costs via property and sales tax revenue the development would generate.

Mayor Kelli Linville said the city has money available to take on some key early projects at the northern end of the site, as well as the Wharf Street roundabout project to smooth the street connection between Cornwall Avenue, Boulevard and State and Forest streets. Details of street projects envisioned as Phase I are:

- The roundabout will cost an estimated $3 million, Money is in hand in the city's street fund, with construction planned for 2013.

- Another $6.5 million in federal grant money is available to build a new street with two names. In keeping with Bellingham tradition, maps show it starting out as Granary Avenue, then veering a bit to the south and becoming Bloedel Avenue, linking up with other new streets called "Commercial Street" (which does not share the alignment of the downtown street of the same name) and Laurel Street (which does.)

- The aforementioned Commercial Street segment has a price tag of $4.4 million.

Port and city staffers have drafted a facilities agreement - still to be reviewed by port commissioners and the City Council - that sets up a complex system for determining when the city will be expected to build early- and late-stage streets, parks and bridges. While the Wharf Street roundabout is slated for 2013, construction of the other projects will depend on the pace of development.

For example, the city's obligation to build Granary and Bloedel avenues is envisioned as beginning no later than Sept. 30, 2017 - but only if the port succeeds in getting a developer to sign the dotted line on a project at the northern end of the waterfront site. Construction of the Commercial Street segment has a similar requirement rather than a fixed date.

Other major street projects have similar development triggers. Port Executive Director Rob Fix said the idea is to help the city avoid "stranded investments," sinking millions into projects but waiting years for private, tax-paying development.

That was always a risk for the city under previous planning concepts that attached dates to each major city investment.

"The city preferred phases based on success of development, rather than a series of years," city planner Sundin said.

Bottom line: Real waterfront development won't begin until people with private investment dollars are on board.

DEVELOPERS SOUGHT

Fix said the port expects to get an early reading of the prospects for that in the next few weeks. The port is already seeking letters of interest from developers who want to get involved in the 10-acre parcel closest to downtown, in and around the Granary.

"I think there's a high level of interest in that section of the development," Fix said.

The port is working with Heartland LLC of Seattle, under a $75,000 contract, to help recruit developers for waterfront projects. Heartland principal Matt Anderson said the prospects will be good if the port and city can provide developers with a high level of certainty about environmental cleanup, land-use regulations and street construction.

"Those are the kinds of things that will set this project apart," Anderson said. "This is going to be a very attractive offering for a variety of different types of developers. ... When the private market sees public agencies working together, that's when they really do start to perk up."

Anderson sees potential for construction of apartments, offices, retail and perhaps a hotel.

While Mayor Linville's team has reached agreement with Fix and port staff on key planning and street construction issues, those agreements still face public scrutiny and review by port commissioners and City Council in 2013.

Not long after the port acquired the G-P site, former Port Executive Director Jim Darling predicted that the planning work would be complete by the end of 2006. But hopes for speedy redevelopment evaporated quickly when the real estate boom collapsed and port and city officials found themselves at a near-impasse on planning issues.

Linville acknowledged public frustration but said the port and city are now in a position to begin to deliver. Although major new developments are still a few years in the future, Linville and port officials hope to be able to offer new waterfront access opportunities by the end of 2013 - most notably a walkway along the breakwater of the old G-P treatment lagoon that the port still hopes to convert to a marina someday.

"I don't like to promise things I don't think I can do," Linville said. "This set of documents promises things I think we can do."

JOIN THE DISCUSSION | Register here

We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.

CONTESTS

Similar stories

  • Port expects Bellingham waterfront proposals by mid-July

    BELLINGHAM - Prospects for a central waterfront renaissance should be clear by mid-July, when the Port of Bellingham expects to receive serious proposals from developers interested in a 10.8-acre portion of the site in and around the Granary building next to Whatcom Waterway.

    On Wednesday, May 15, port officials sent out a 30-page "request for proposals" to developers, who have until July 10 to provide their plans for waterfront projects, as well as evidence of their financial ability to carry out those plans. That includes the money to buy or lease waterfront development sites from the port at market rates.

    Interested developers have been invited to submit proposals for all or part of the 10.8 acre portion at the northeast end of the 237-acre waterfront site, much of which was formerly occupied by the Georgia-Pacific Corp. pulp and paper mill.

  • Bellingham waterfront plan ready for community feedback

    BELLINGHAM - It's taken years to get to this point, but it's time for one more important round of community input about the redevelopment of Bellingham's waterfront.

    Last week city and Port of Bellingham staff presented a framework for phased redevelopment of about 237 acres of waterfront to the city's planning commission. Public hearings on the plan are scheduled for 7 p.m. on the next two Thursdays, March 21 and 28, in the Bellingham City Council chambers.

    The original March 14 presentation airs at 7 p.m. Sunday, March 17, on the city's television channel, BTV10 (Comcast channel 10 in Bellingham), and is available on its website, cob.org. The city website also has public documents for the community to review.

  • Bellingham, port officials strike back at Pike’s waterfront criticisms

    BELLINGHAM - The city's former mayor said those now in charge of coming up with a redevelopment plan for the waterfront aren't listening to the will of the community.

    "If you're an elected official, and the public overwhelmingly wants something, you should be responsive to the public," Dan Pike said on Thursday, Feb. 7, at a talk on past and present planning for the waterfront, part of the Huxley College of the Environment Speaker Series.

    He had an audience of about 200 people, many of them students, on the Western Washington University campus.

  • Bellingham, port officials strike back at Pike’s waterfront criticisms

    BELLINGHAM - The city's former mayor said those now in charge of coming up with a redevelopment plan for the waterfront aren't listening to the will of the community.

    "If you're an elected official, and the public overwhelmingly wants something, you should be responsive to the public," Dan Pike said on Thursday, Feb. 7, at a talk on past and present planning for the waterfront, part of the Huxley College of the Environment Speaker Series.

    He had an audience of about 200 people, many of them students, on the Western Washington University campus.

  • Nighttime cleanup starts on portion of contaminated Bellingham shoreline

    BELLINGHAM - Cleanup will start Monday night, Jan. 7, on a small section of shoreline near downtown Bellingham contaminated with petroleum, according to the Washington Department of Ecology.

    Crews from Bellingham's Ram Construction will dig out about 80 truckloads of petroleum-contaminated soil and sediment from a 5,000-square-foot portion of beach at the Central Waterfront cleanup site, near the west end of C Street.

    They will then install a liner to prevent recontamination and rebuild the beach with clean material.