Bellingham, port officials strike back at Pike’s waterfront criticisms

Published: Feb. 8, 2013 at 9:11 a.m. PST
0 comments

BELLINGHAM - The city's former mayor said those now in charge of coming up with a redevelopment plan for the waterfront aren't listening to the will of the community.

"If you're an elected official, and the public overwhelmingly wants something, you should be responsive to the public," Dan Pike said on Thursday, Feb. 7, at a talk on past and present planning for the waterfront, part of the Huxley College of the Environment Speaker Series.

He had an audience of about 200 people, many of them students, on the Western Washington University campus.

A member of the current mayor's staff and the executive director of the Port of Bellingham both said after the talk that Pike paints an incomplete and sometimes inaccurate picture of the waterfront plans.

Pike gave the port and Mayor Kelli Linville's administration credit for making real progress on the plan over the past year, after Linville replaced him. But the bad news, he said, is in "where that progress seems to be taking us."

Pike criticized the likely demolition of historic waterfront buildings, the loss of park space and a proposal for what in his view is an overly expensive marina.

City special projects manager Tara Sundin and port Executive Director Rob Fix both said Pike's presentation didn't do justice to the specifics of the waterfront plan. Sundin attended the talk.

While some proposed open space has been eliminated near the log pond, on the Whatcom Waterway, there is no loss of overall park acreage, Sundin said. As for the marina, it isn't an immediate concern.

"It is in a much later phase of the plan," Fix said.

Pike's interest in historic buildings centers on the port-owned Granary, a derelict egg processing center on Roeder and Central avenues. With its distinctive look, it would be an ideal entryway to the new waterfront, he said.

Pike said the city wanted to tear the building down to build a road, and the port has already made up its mind that it can't be renovated.

Not necessarily true, Sundin said. The city is considering an alternate route into the development that keeps the Granary intact.

Far from dismissing a resurrection of the Granary, Fix said early development proposals for the building show promise.

"Two different, separate groups have plans to develop it," Fix said.

Fix and Sundin both emphasized the role the public will have in shaping the waterfront. The city Planning Commission holds its first public hearing on the waterfront draft master plan on March 21.

"He's entitled to his opinions," Sundin said of Pike, "and so is everyone else."

JOIN THE DISCUSSION | Register here

We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.

PHOTOS
CONTESTS

Similar stories

  • Bellingham, port officials strike back at Pike’s waterfront criticisms

    BELLINGHAM - The city's former mayor said those now in charge of coming up with a redevelopment plan for the waterfront aren't listening to the will of the community.

    "If you're an elected official, and the public overwhelmingly wants something, you should be responsive to the public," Dan Pike said on Thursday, Feb. 7, at a talk on past and present planning for the waterfront, part of the Huxley College of the Environment Speaker Series.

    He had an audience of about 200 people, many of them students, on the Western Washington University campus.

  • Bellingham waterfront plan ready for community feedback

    BELLINGHAM - It's taken years to get to this point, but it's time for one more important round of community input about the redevelopment of Bellingham's waterfront.

    Last week city and Port of Bellingham staff presented a framework for phased redevelopment of about 237 acres of waterfront to the city's planning commission. Public hearings on the plan are scheduled for 7 p.m. on the next two Thursdays, March 21 and 28, in the Bellingham City Council chambers.

    The original March 14 presentation airs at 7 p.m. Sunday, March 17, on the city's television channel, BTV10 (Comcast channel 10 in Bellingham), and is available on its website, cob.org. The city website also has public documents for the community to review.

  • Waterfront's impact on downtown Bellingham could be issue

    BELLINGHAM - The negative impacts of a booming waterfront on downtown businesses is emerging as a concern as waterfront redevelopment plans get public scrutiny.

    At a Thursday, May 9, session of the Bellingham Planning Commission, some commissioners said waterfront businesspeople have expressed fears about how a revitalized waterfront would affect them.

    "They are in fact worried that the city is turning a shoulder to downtown in favor of this new, glitzy project," said Planning Commission Chairman Tom Grinstad, an architect.

  • Port expects Bellingham waterfront proposals by mid-July

    BELLINGHAM - Prospects for a central waterfront renaissance should be clear by mid-July, when the Port of Bellingham expects to receive serious proposals from developers interested in a 10.8-acre portion of the site in and around the Granary building next to Whatcom Waterway.

    On Wednesday, May 15, port officials sent out a 30-page "request for proposals" to developers, who have until July 10 to provide their plans for waterfront projects, as well as evidence of their financial ability to carry out those plans. That includes the money to buy or lease waterfront development sites from the port at market rates.

    Interested developers have been invited to submit proposals for all or part of the 10.8 acre portion at the northeast end of the 237-acre waterfront site, much of which was formerly occupied by the Georgia-Pacific Corp. pulp and paper mill.

  • Port of Bellingham, city have new strategy for building up waterfront

    BELLINGHAM - When the Port of Bellingham acquired the Georgia-Pacific Corp. pulp and paper mill site, the potential cost of environmental cleanup was a big, worrisome unknown.

    The port's preliminary estimate of that cost was $40.3 million, but nobody knew for sure the extent of contamination from decades of pulp and chemical operations that involved mercury, among other things, or what it would cost to deal with that contamination in a way the Washington Department of Ecology would accept.

    So in late 2004, before closing the deal with G-P, port officials arranged the purchase of a complex insurance policy to cover potential overruns.