A section of Tilley Road in Tumwater will be reduced to one lane next week as construction crews install a sewer main, according to a news release.
Work begins Monday from 8 a.m.-4 p.m. on Tilley Road south of 88th Avenue. Work is expected to be completed by next Friday depending on weather.
Work already was delayed a week because of weather conditions and utility conflicts.
The sewer main will extend utility services to the Tilley Road Industrial Park.
Drivers who frequent the area should expect delays and use alternate routes if possible, the release said.
For information, call Tumwater Public Works at 360-754-4140.
ckrotzer@theolympian.com


JOIN THE DISCUSSION | Register here
We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.