Ferndale officials eager to fix hard-water problem, but worry about cost

Published: March 3, 2013 at 10:00 p.m. PSTUpdated: March 5, 2013 at 2:46 p.m. PST
0 comments
Wes Herman, owner of The Woods Coffee, ducks under a ventilation shaft as he walks past the water softening system installed in a utility closet at the company's Ferndale location Wednesday, Feb. 27, 2013. Herman estimated the system cost $10,000 to install. (COLIN DILTZ/THE BELLINGHAM HERALD)

FERNDALE - The will is there. But still unknown late last week were the options the city has for fixing its hard-water problem, and how much it would cost.

City Council will hear a report Monday, March 4, from engineers hired in December 2012 to come up with water-softening options.

"We don't know what the consultant's recommendation is going to be. We don't know what it's going to cost. We're all hoping it's not an unreasonable cost," said council member Mel Hansen. "The mayor and most on the council have agreed to do something to get that water acceptable to our citizens."

Council member Cathy Watson said a fix for the hard-water problem is a high priority.

"If we can do something for a reasonable price, we should do it," she said.

Report details weren't available as of Friday afternoon, March 1, said city Administrator Greg Young. A rough estimate by a different engineer put the cost of a water softener in the treatment plant at $1.2 million to $1.4 million.

The city converted in December 2011 from Nooksack River water supplied by the Public Utility District of Whatcom County to its own well water. Afterward, the response from water customers was swift and almost entirely critical. Residents, businesses and schools complained of a poor taste or a degree of hardness that stained and damaged glassware and appliances.

Ferndale's water in 2012 measured high on the hardness scale, at 154 parts per million of calcium carbonate. RH2 Engineering, which guided the city through the conversion to well water, measured hardness at less than 120 ppm from 2007 to 2010.

Wilson Engineering, the consultant putting together the report for Monday, was asked to come up with systems that could bring the hardness down to 70 ppm, about what it was before the switch to well water.

Some council members argued that 2012 might have been an unusual year for water hardness, and the city should take more measurements before seeking a solution.

The mayor, who hears the brunt of the complaints, has been urging council members to fix the problem. He'll encourage them Monday to tell the Public Works Department which softening option to pursue.

Council member Jon Mutchler said he's optimistic the city can afford softer water. The city received a $200,000 refund from the PUD for leaving the utility after investing in some of its improvements. Also, a new accounting requirement will return about $100,000 from administrative funds to the city's water fund, Mutchler said.

"We've had record housing starts in January," he said. "All those customers are paying water hookup fees. They'll pay monthly water/sewer bills. I have a sense in my own thinking on this that we're going to be able to have the resources."

"We're going to try real hard not to raise rates to fix this," he said.

The study session Monday starts at 5 p.m. at Community Resource Center, 5694 Second Ave.

JOIN THE DISCUSSION | Register here

We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.

CONTESTS

Similar stories

  • Ferndale officials never saw water problems coming

    FERNDALE - City officials did not know in advance that hard water from Ferndale's wells would stain or damage fixtures and appliances.

    The consultant hired to steer Ferndale through the conversion from Nooksack River water to well water last year was not looking for this problem, according to data logs and memos from the city's water treatment plant and the consultant, RH2 Engineering.

    In an interview, RH2 project manager Dan Burwell said water hardness is not a concern when testing a new water source because minerals are not a health hazard. It isn't even an inconvenience, the consultant said, as long as residents and businesses maintain appliances and equipment properly.

  • Ferndale finds $2M solution to its hard water problem

    Hard well water, a problem that has vexed Ferndale leaders and residents for more than a year, appears to have a workable solution.

  • Ferndale councilman seeks second term

    FERNDALE - Jon Mutchler, pastor and musician, would like to continue wearing another hat in the city - that of city council member.

    Mutchler, 53, announced Monday, April 29, he will seek a second term on the council. He defeated incumbent Ken Downey by five votes in a recount in 2009.

    Mutchler is a fiscal conservative who voted with the minority against a 3 percent property tax hike for 2013.

  • Council might ask voters to pay for Ferndale library

    FERNDALE - City Council members are on a tight deadline to decide how to pay for $1.05 million they have committed over the past four years to a new library building.

    There's a lot at stake and a lot to consider, so Mayor Gary Jensen has cleared the rest of the council's agenda for its Monday, March 4, meeting, to focus on the library.

    If construction doesn't begin by the end of August, a $250,000 grant from Norcliffe Foundation for the $5 million project will be withdrawn. If the council wants to ask Ferndale voters for a property tax increase to cover the $1.05 million, it must do so next week.

  • Business-friendly councilman to run again in Ferndale

    FERNDALE - A City Council member who has worked to enhance economic growth will seek a second term.

    Brent Goodrich, 55, is former chairman of the Ferndale Economic Development Commission. When the council debated changing traffic impact fees for new businesses in 2012, Goodrich was among the strongest advocates for lower fees.

    Goodrich has written two guest editorials published in The Bellingham Herald supporting the Gateway Pacific Terminal for coal exporting at Cherry Point.