Richland engineers reflect on Fukushima nuclear disaster response

Published: March 10, 2013 at 11:35 p.m. PDTUpdated: March 12, 2013 at 9:51 p.m. PDT
0 comments
A system to clean radioactively contaminated emergency cooling water after the Fukushima nuclear disaster two years ago is installed in spring 2011. Staff at AECOM in Richland under Kurion’s direction raced to create a detailed design for the system. (PHOTOS COURTESY OF KURION)

Two years ago, Richland engineers were about to start a marathon effort to quickly design the details of a system that would keep radioactively contaminated water from flowing from damaged Fukushima reactors into the Pacific Ocean.

They not only succeeded, but the system AECOM workers in Richland designed under Kurion's direction continues to operate today to clean contaminated water at the Fukushima, Japan, Dai-ichi Nuclear Plant. It is expected to continue operating for years to come.

On March 11, 2011, a magnitude-9 earthquake was followed by a tsunami that caused a full meltdown at three reactors at the Fukushima plant. With no functioning cooling system, the Tokyo Electric Power Co. resorted to pouring millions of gallons of seawater into the reactors to cool them.

But by the middle of April, the plant's basements and buildings were filling with water contaminated from the failed fuel in the reactors. The upcoming start of the rainy season threatened to flood the plant, spilling the contaminated water out of the complex to flow into the ocean.

Kurion, an Irving, Calif., waste treatment company that has since moved its engineering and technology work to Richland, convinced the Tokyo Electric Power Co. that it was in a unique position to help. It had a proprietary chemical compound for an ion exchange system that is particularly good at stripping cesium, the main contaminant, from the water.

And unlike some other chemical compounds used in ion exchange water treatment systems, it has low sensitivity to salt water and is resistant to radiation.

But the concept needed to be turned into a system that could fit in the limited space available at the Daiichi Nuclear Plant and could start operating before huge volumes of contaminated water flooded into the ocean.

Kurion picked AECOM in Richland to execute the design under its direction.

"They almost lived in the office for almost a month," said Jim Homan, then the senior operations manager for AECOM's Nuclear Division. "To think you were going to design and build something in a month is ridiculous. But it was an emergency."

Under Kurion's direction, the team did the detailed engineering and executed the design of a system of pumps, piping, power and controls and ion exchange components, together with radiation shielding. Design changes were constant as new information became available about the damaged plant.

The equipment was organized in eight skids -- or frameworks about the size and shape of a commercial shipping container -- with six of them eventually were installed and operated at Fukushima.

They would be flown to Japan and needed to fit within the confines of the Soviet-era Antonov An-225 Mriya. It's the largest cargo aircraft in the world and the only plane that could transport them.

Within five weeks, the system was designed, built and shipped to Japan. The skids weighed about 22 metric tons each when shipped on three planes, but installed with shielding and vessels, some weigh nearly 100 tons.

The system was assembled in Japan in nine days and on June 14, 2011, was tested using clean water. Three days later it started treating contaminated water.

After the Three Mile Island partial nuclear meltdown in 1979, it took 18 months for a cesium removal system to start operating, according to AECOM. But the Fukushima, Japan, system designed in Richland and built in Colorado and California was removing radioactive cesium from the water fewer than 100 days following the tsunami.

The rainy season came early in 2011. Had Kurion's treatment system started operating about a week later, contaminated water would have started flooding from the plant back into the ocean, said John Raymont, Kurion president.

"It was a very dramatic race against time," he said.

A year after the tsunami hit the plant, the treatment system had processed 36 million gallons of contaminated water and removed 8.4 million curies of cesium.

Now it has cleaned 45.7 million gallons of radioactive water, or enough water to cover a football field 130 feet high, according to Kurion.

The system continues to operate to clean water used to cool the water and groundwater that is leaking into the contaminated plant.

JOIN THE DISCUSSION | Register here

We welcome comments. Please keep them civil, short and to the point. ALL CAPS, spam, obscene, profane, abusive and off topic comments will be deleted. Repeat offenders will be blocked. Thanks for taking part — and abiding by these simple rules. A thorough explanation of rules of conduct can be found in our Terms of Service. If you have any questions, including why your comment may not be showing immediately after you submit it, be sure to visit the commenting FAQ.

MORE PHOTOS
CONTESTS

Similar stories

  • Kurion pitches new vitrification system for Hanford tank waste

    Kurion is proposing tank-side vitrification of radioactive waste as a way to address Hanford’s issues with leaking underground tanks.

    The small company, which has opened a 13,000-square-foot testing facility in Richland, is not proposing to replace the $12.2 billion vitrification plant being built at Hanford to treat up to 56 million gallons of radioactive waste now held in underground tanks.

    Instead, it is offering a supplemental treatment technology that it says could be ready to treat the low-activity radioactive waste that makes up the majority of the tank waste by late 2014.Kurion believes its system is a more flexible way to treat waste, because waste is vitrified into a stable glass form in small, customized batches.

  • Japan nuclear plant probes leak from new tank

    Workers at a crippled Japanese nuclear plant are investigating why highly radioactive water leaked from a new storage tank, amid concerns that the problem could further hamper cleanup efforts.

  • Fukushima plant steps closer to fuel-rod removal

    Damaged vehicles, twisted metal and other debris remain strewn about Japan's crippled nuclear power plant. Scores of black and gray pipes and hoses cover the ground, part of the makeshift system to pump water into the damaged reactors to keep them from overheating.

  • France's Hollande visits Japan to push nuke ties

    French President Francois Hollande arrived in Japan on Thursday for a visit expected to focus on closer cooperation in nuclear energy technologies and on Prime Minister Shinzo Abe's economic strategies.

  • Nuclear plants ordered to upgrade vents

    WASHINGTON -- U.S. nuclear power plants must upgrade ventilation systems at 31 reactors with designs similar to those that melted down two years ago in Japan, under a Nuclear Regulatory Commission order, issued Tuesday, that stops short of requiring filtered vents, as some safety advocates and NRC's staff had urged.

    Among those reactors is the Columbia Generating Station operated by Energy Northwest near Richland. It began planning to install hardened, or reinforced, vents at a cost of $25 million to $30 million a year ago, following an initial NRC order, said Energy Northwest spokesman Mike Paoli. Energy Northwest already has the capability to vent the reactor in case of a catastrophic natural emergency.

    The hardened vents should be installed during the fuel outage in spring 2015 or 2017.